How long should I allow for installation
You should allow no more than 15 minutes to land a unit with the crane whether on the ply deck or structural steelwork. If the unit requires core wall plates to be drilled and bolted you should allow an hour per unit for one operative.
-
Are holes for M&E services protected?
Yes all penetrations come covered with a sacrificial cover plate.
-
Are lifting eyes included?
Yes all units have 4 lifting points welded to them. We supply 4 no. certified shackles at the start of the project free of charge.
-
Can you install?
No we are a supplier only, installation is so straight forward there would be no point in us offering that services.
-
Do you provide drawings?
Yes on every project , our contracts managers and 3D Modelling team, work closely with the client team to produce project specific drawings for approval.
-
The M&E design isn’t complete, can I still get a fixed price?
Yes. Our price includes for either plain Durbar plates or Durbar plates pre-cut for M&E services. We provide a second fixed schedule of rates for replacement M&E plates if they were initially supplied as plain plates.
-
What is your lead time?
Generally 8 weeks from order although exceptions can be made.